Project Control: Scope Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • Program/Project Change Requests
  • Approved Program/Project Change Requests
  • Updated Business Case
  • Updated Scope Statement
  • Updated Schedule
  • Updated Resource Requirements
  • Program Manager
  • Program Steering Committee
 



Objectives:

The purpose of Scope Management is to ensure that the program includes all the work (and only the work) required so that the program's objectives are met.

Description:

This activity includes:

* These can be direct changes at the program level or changes to projects under the program.

 

Project Control: Schedule Management

Inputs Outputs Who Performs Who Reviews Tools
  • Resource Requirements
  • Schedule
  • Resource Constraints
  • Updated Schedule
  • Updated Program Summary Report
  • Program Manager
  • PMO
  • Program Steering Committee
  • Resource Managers
  • MS Project
  • Other scheduling tools



Objectives:

The purpose of Schedule Management is to control changes to the program schedule so that the impact of changes can be identified, mitigated where necessary and communicated to stakeholders.

Description:

This activity includes:

Instructions:

The program manager meets with the project managers on a regular basis (at least once each week) to:

 

Project Control: Cost Management

Inputs Outputs Who Performs Who Reviews Tools
  • Program Schedule
  • Business Case
  • Project's Status Reports (cost plans & resource requirements)
  • Updated Program Summary Report
  • Updated Business Case
  • Program Manager
  • Program Steering Committee
  • PMO
 



Objectives:

The purpose of Cost Management is to review program costs so that issues associated with costs (staffing, materials, etc.) are identified and addressed, minimizing impact to program costs, schedule, quality as well as the program's overall objectives (benefits).

Description:

Individual project cost plans (including both expense and capital costs) are used to track each project's actual spending on a monthly basis.  These numbers are placed in Program Summary Report which calculates program totals.  This is used to identify

This activity includes:

Instructions:

The program manager monitors the individual project status reports to:

 

Project Control: Quality Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • ISO Standards
  • SORCAs
  • Project Documentation
  • GIS PMP
  • Development Standards
  • Updated Control Activities
  • Updated Project Documentation
  • Program Manager
  • PMO QA
  • Auditors
  • Managers
  • PMO
Add links to CPP, ISO, SORCAs?



Objectives:

The purpose of Quality Management is to identify, track and measure the project objectives and performance, and to ensure that appropriate standards and processes are followed so that the program will meet stakeholder expectations.

Description:

Quality management covers the program, the program's projects and all the products produced by the program.  This activity includes planning, measuring and auditing compliance of the program, projects and products to ISO 9001:2000, Sarbanes-Oxley, corporate policies and practices and GIS policies, processes and standards.  If the program manger discovers that the project is off course on any of these, it is his/her responsibility to develop and implement corrective action plans. 

 

Project Control: Resource Management

Inputs Outputs Who Performs Who Reviews Tools
  • Resource Requirements (from status report)
  • Schedule
  • Purchase Request (if needed)
  • Statement of Work (if needed)
  • Updated Resource Requirements (in status report)
  • Updated Capacity Plan
  • Program Manager (resp.)
  • Project Managers
  • Resource Managers
  • PMO
 



Objectives:

The purpose of Resource Management is to identify, obtain and manage all project resources (all goods and services, including human resources) so that the appropriate resources are available when needed throughout the program life cycle.

Description:

This activity includes:

Instructions:

The program manager meets with the project managers on a regular basis (at least once each week) to:

 

Project Control: Communication Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • Escalation Guidelines
  • Project's Status Reports
 
  • Communication Plan
  • Program Summary Report
  • Program Folder
 
  • Sponsor
  • Process Owner
  • Project Manager (resp.)
  • Program Steering Committee
  • Program Team
  • Corporate Communication (if applicable)
  • Managers
  • Stakeholders
  • Business Users

 

 



Objectives:

The purpose of Communication Management is to develop, manage and execute the program communication plan so that the right people receive the right information at the right time throughout the program life cycle.

Description:

This activity consists of developing the program communication plan, setup and maintenance of the program folder, issue escalation, providing status reports presenting at the monthly project reviews, conducting regular meetings with project managers and with the program steering committee.

Part of the overall communication plan includes the Escalation Guidelines.  This document provides some basic guidelines to be used in escalating issues or risks which are outside of the program team's sphere of influence. 

Setup and Maintain Folder Instructions:

Program Summary Report Instructions:

Need to review the template and update instructions here:  The purpose of the Status Report is to communicate project status to stakeholders, managers and other project teams.  The master workbook remains in the root folder while a copy is filed in the appropriate week’s folder.  They are due by 5:00 pm each Tuesday.  This is a firm cut-off as the data will be uploaded to the database beginning first thing Wednesday mornings.

It is mandatory that this template is used since it is used to update the GIS Project Scorecard and is the format used for monthly project reviews.

For detailed instructions on the Status Report, view the Status Report User's Guide.

Monthly Project Reviews:

All active GIS programs/projects are reviewed on a monthly basis.  Program managers use their program summary report to present the status of the program to the GIS management team, other program/project managers, and other key stakeholders. 

Lessons learned for completed programs are also presented at the monthly project reviews.  Program managers use their completed lessons learned document for the presentation.

NOTE:  It is the program manager's responsibility to ensure that their report or lessons learned document are filed in the appropriate location by the documented deadlines in preparation for the monthly project reviews.  If they miss those deadlines, it is their responsibility to bring three copies of their document to the review.

 

Project Control: Risk Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • Requirements Document
  • Resource Requirements
  • Assumptions & Constraints
  • Risk Mitigation Plan
  • Sponsor
  • Project Manager (resp.)
  • Project Team
  • Requestor
  • Stakeholders
  • Area Managers
  • TDMs
  • Infrastructure Team Leads
  • Managers
  • Stakeholders
 



Objectives:

The purpose of Risk Management in the Project Control phase is to identify, analyze and document the project risks so that plans can be made to minimize the impact that unfavorable events would have on the project objectives (schedule, budget, resources, deliverables and defects).

Description:

Risk is defined as “an uncertain event or condition that, if it occurs, has a positive or a negative effect on a project objective”.  There are times when plans to mitigate risks are outside the sphere of the project team's influence.  See the Escalation Guidelines for assistance.

Instructions:

NOTE:  Through out the life cycle of the project, more risks may be identified.  Those should be assessed as above, approved by the sponsor and requestor and incorporated into a new version of the document.  Do not overwrite the baseline version or subsequent versions – there should be a version for each change after the initial baseline document.

 

Project Control: Integration Management

Inputs Outputs Who Performs Who Reviews Tools
  • Everything Related to the Project
  • Integration of all Project Activities and Documents
  • Assumptions & Constraints
  • Actions Items & Issues
  • PMP Checklist
  • Sponsor
  • Project Manager (resp.)
  • Project Team
  • Requestor
  • Stakeholders
  • Managers
 



Objectives:

The purpose of Integration Management in the Project Control phase is to ensure that the various elements of the project are properly coordinated so that the product will meet stakeholder expectations.

Description:

Integration Management is the sum of all the project activities and documents.  It ensures that all aspects of the project fit together without conflict.  In the event of a “program”, it integrates the management areas of the sub-projects. 

This activity includes:

PMP Checklist Instructions:

The PMP Checklist is a tracking tool used to indicate at a glance where a project is in the project life cycle.  It is used:

As deliverables are developed the project manager indicates the date completed on the PMP Checklist.

If an activity isn't required for a project the project manager puts N/A in the Date Completed column and records an explanation of why the activity is not required for the specific project.  NOTE:  If the item deemed as not necessary for a project requires an approval, the project manager must obtain approval/agreement from the sponsor and requestor that the activity isn't required.