Project Control: Scope Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • Requirements Document
  • Approved Project Change Requests
  • Updated Business Case
  • Updated Scope Statement
  • Updated Requirements Documents
  • Updated Schedule
  • Updated Dashboard
  • Updated Resource Requirements
  • Sponsor
  • Project Manager (resp.)
  • Requestor
  • Managers
  • Project Team
  • Stakeholders
 



Objectives:

The purpose of Scope Management in the Project Control phase is to ensure that the project includes all the work required so that the project is completed successfully.  It defines and controls what is or is not included in the project.

Description:

This activity is the maintenance of the Business Case, Scope Statement and Requirements Document through the project change request process throughout the project lifecycle.  The Business Case, Scope Statement and Requirements Document are all controlled documents which must be approved upon completion and must be re-approved any time changes are made. 

Change Control Instructions:

Each project team should have a Change Control Board (CCB) which is used to determine how to disposition requested changes.  The CCB is comprised of the sponsor, requestor, project manager and other key stakeholders identified by the team.  Significant changes must go back through the GIS Approval Committee process.  Contact a PMO member to get on the agenda for review or for assistance in deciding if the changes are considered significant.  Depending on the impact of the changes, the project may need to also go back to the GIS PST.

·         Project manager sends the project change request form to the PMO.

·         PMO includes the project change request in the packet for the next Approval Committee meeting.

·         PMO communicates committee’s decision to the project manager.

 

Project Control: Schedule Management

Inputs Outputs Who Performs Who Reviews Tools
  • Requirements Document
  • Resource Requirements
  • Schedule
  • Resource Constraints
  • Updated Schedule
  • Project Manager (resp.)
  • Sponsor
  • Managers
  • Metric SMEs
  • PMO
  • Stakeholders
  • MS Project
  • Other scheduling tools



Objectives:

The purpose of Schedule Management in the Project Control phase is to control changes to the project schedule so that the impact of the changes can be identified, mitigated where necessary and communicated to stakeholders.

Instructions:

The project manager should review the schedule on a regular basis (at least once each week) to:

 

 

Project Control: Cost Management

Inputs Outputs Who Performs Who Reviews Tools
  • Cost Plan (from status report)
  • Resource Requirements (from status report)
  • Project Schedule
  • Requirements Document
  • Updated Status Report
  • Project Manager (resp.)
  • GIS Managers
 



Objectives:

The purpose of Cost Management in the Project Control phase is to review project costs to so that issues associated with costs (staffing, materials, etc.) are identified and addressed, minimizing impact to project costs, schedule and quality.

Description:

The cost plan is a way to identify estimated projects costs, both expense and capital.  These costs should be broken out by each month of the project, throughout the project life cycle.  The summary of this information is recorded, tracked and monitored in the status report.

Instructions:

 

 

Project Control: Quality Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • Requirements Document
  • Measurement Guidelines
  • ISO Standards
  • Project Documentation
  • PMP
  • Development Standards
  • Updated Control Activities
  • Updated Project Documentation
  • PMO
  • Project Manager (resp.)
  • Project Team
  • Business Users
  • Sponsor
  • Managers
  • Project Team
  • Requestor
  • Stakeholders
 



Objectives:

The purpose of Quality Management in the Project Control phase is to identify, track and measure the project objectives and performance, and to ensure that appropriate standards are followed so that the product will meet the stakeholder expectations.

Description:

Quality management covers both the project and the product produced by the project.  This activity includes planning, measuring and auditing compliance of the project and product to ISO 9001:2000, Sarbanes-Oxley, corporate policies and practices, requirements, etc.    

Instructions:

 

Project Control: Resource Management

Inputs Outputs Who Performs Who Reviews Tools
  • Requirements Document
  • Resource Requirements (from status report)
  • Project Solution Approach
  • Schedule
  • Purchase Request (if needed)
  • Statement of Work (if needed)
  • Updated Resource Requirements (in status report)
  • Updated Capacity Plan
  • Infrastructure Team Leads
  • Managers
  • Project Manager (resp.)
  • TDMs
   



Objectives:

The purpose of Resource Management in the Project Control phase is to identify, obtain and manage all project resources (all goods and services, including human resources) so that the appropriate resources are available when needed throughout the life cycle of the project.

Description:

Obtaining resources is an iterative process throughout all phases of the project.  Early in the Analyze phase the project manager identifies as best as possible the roles (skills) and effort needed to complete the project plan.   The project manager estimates the project duration and targets using the Resource Requirements sheet from the Status Report (instructions are in the Status Report User's Guide).  Any known computer resources which are critical to the success of the project should be documented on the Critical Computer Resource Log (see instructions included in the template).

Resources may come from many organizations, not only GIS.  It is especially important to gain approval and commitment for business resources needed by the project team. 

Resource requirements are continuously updated throughout the life of the project as the project progresses and more detail is known.  Updated effort forecasts are entered in the monthly capacity plan.

Obtaining Internal Resource Instructions:

Obtaining External Resource Instructions:

 

The procurement processes are outside of the GIS PMP and are managed by the Sourcing department.  The following URL provides links to related forms, instructions and information:  http://gandalf.stortek.com/wwsrc/purchasing.shtml.

See your manager for assistance in determining the specific steps which must be followed for the individual project's circumstances.

 

Document Baseline & Version Control Instructions:

 

Project Control: Communication Management

Inputs Outputs Who Performs Who Reviews Tools
  • GIS PMP
  • Business Case
  • Scope Statement
  • Requirements Document
  • Escalation Guidelines
  • Test Repository Document
  • Communication Plan
  • Status Report
  • Project Folder
  • Best Practice Candidate Materials and Process Improvements for Testing
  • Business User
  • Sponsor
  • Process Owner
  • Project Manager (resp.)
  • Project Team
  • Requestor
  • Test Manager
  • Quality Assurance
  • Corporate Communication (if applicable)
  • Managers
  • Stakeholders
 



Objectives:

The purpose of Communication Management in the Project Control phase is to develop, manage and execute the communication plan so that the right people receive the right communication at the right time throughout the project lifecycle.

Description:

This activity consists of developing the communication plan, setup and maintenance of the project folder, issue escalation, providing status reports and monthly project reviews.

Part of the overall communication plan includes the Escalation Guidelines.  This document provides some basic guidelines to be used in escalating issues or risks which are outside of the project team's sphere of influence. 

Setup and Maintain Folder Instructions:

Status Report Instructions:

The purpose of the Status Report is to communicate project status to stakeholders, managers and other project teams.  The master workbook remains in the root folder while a copy is filed in the appropriate week’s folder.  They are due by 5:00 pm each Tuesday.  This is a firm cut-off as the data will be uploaded to the database beginning first thing Wednesday mornings.

It is mandatory that this template is used since it is used to update the GIS Project Scorecard and is the format used for monthly project reviews.

For detailed instructions on the Status Report, view the Status Report User's Guide.

Monthly Project Reviews:

All active GIS projects are reviewed on a monthly basis.  Project managers use their status report to present the status of their project to the GIS management team, other project managers, and other key stakeholders. 

Lessons learned for completed projects are also presented at the monthly project reviews.  Project managers use their completed lessons learned document for the presentation.

NOTE:  It is the project manager's responsibility to ensure that their status report or lessons learned document are filed in the appropriate location by the documented deadlines in preparation for the monthly project reviews.  If they miss those deadlines, it is their responsibility to bring three copies of their documents to the review.

 

Project Control: Risk Management

Inputs Outputs Who Performs Who Reviews Tools
  • Business Case
  • Scope Statement
  • Requirements Document
  • Resource Requirements
  • Assumptions & Constraints
  • Risk Mitigation Plan
  • Sponsor
  • Project Manager (resp.)
  • Project Team
  • Requestor
  • Stakeholders
  • Area Managers
  • TDMs
  • Infrastructure Team Leads
  • Managers
  • Stakeholders
 



Objectives:

The purpose of Risk Management in the Project Control phase is to identify, analyze and document the project risks so that plans can be made to minimize the impact that unfavorable events would have on the project objectives (schedule, budget, resources, deliverables and defects).

Description:

Risk is defined as “an uncertain event or condition that, if it occurs, has a positive or a negative effect on a project objective”.  There are times when plans to mitigate risks are outside the sphere of the project team's influence.  See the Escalation Guidelines for assistance.

Instructions:

NOTE:  Through out the life cycle of the project, more risks may be identified.  Those should be assessed as above, approved by the sponsor and requestor and incorporated into a new version of the document.  Do not overwrite the baseline version or subsequent versions – there should be a version for each change after the initial baseline document.

 

Project Control: Integration Management

Inputs Outputs Who Performs Who Reviews Tools
  • Everything Related to the Project
  • Integration of all Project Activities and Documents
  • Assumptions & Constraints
  • Actions Items & Issues
  • PMP Checklist
  • Sponsor
  • Project Manager (resp.)
  • Project Team
  • Requestor
  • Stakeholders
  • Managers
 



Objectives:

The purpose of Integration Management in the Project Control phase is to ensure that the various elements of the project are properly coordinated so that the product will meet stakeholder expectations.

Description:

Integration Management is the sum of all the project activities and documents.  It ensures that all aspects of the project fit together without conflict.  In the event of a “program”, it integrates the management areas of the sub-projects. 

This activity includes:

PMP Checklist Instructions:

The PMP Checklist is a tracking tool used to indicate at a glance where a project is in the project life cycle.  It is used:

As deliverables are developed the project manager indicates the date completed on the PMP Checklist.

If an activity isn't required for a project the project manager puts N/A in the Date Completed column and records an explanation of why the activity is not required for the specific project.  NOTE:  If the item deemed as not necessary for a project requires an approval, the project manager must obtain approval/agreement from the sponsor and requestor that the activity isn't required.